Labour shortage and material crunch delay Hinjewadi–Shivajinagar metro launch
The Hinjewadi–Shivajinagar metro launch faces delays due to labour shortages linked to the West Bengal elections and a material crunch tied to the West Asia conflict. The first phase is now expected to commence on June 15, 2026, with 12 stations, while the remaining 11 are targeted by October; multiple prior schedule revisions are noted, and safety approvals are pending.
Why It Matters
Delays affect Pune's IT hub connectivity and public transport rollout under PPP, with ongoing monitoring and safety approvals required before operations.
Timeline
6 Events
First phase plan and challenges reported
As reported on May 3, 2026, the first phase is planned to begin on June 15, 2026, covering 12 stations, with the remaining 11 stations expected to be operational by October. Operations require approval from the Commissioner of Metro Railway Safety and the plan has not yet been submitted in writing. Labour shortage due to West Bengal assembly elections and a material crunch from the West Asia conflict are cited as key delays. PMRDA has stepped up monitoring after a water leak near the Pashan ramp was found during a recent inspection near Savitribai Phule Pune University Chowk.
Timeline revised to May 2026
The project timeline was revised again, to May 2026.
Timeline revised to March 2026
The project timeline was revised again, to March 2026.
Timeline revised to December 2025
The project timeline was revised again, to December 2025.
Timeline revised to September 2025
The project timeline was revised to September 2025 (from March 2025).
Initial expectation: March 2025 start
The metro service was initially expected to start in March 2025.